G18 Infra

  • Cleaning the bathroom and laying down fleece.
  • Lay the skirting boards.
  • Lay the network cables from the sub-distribution board to the parapet ducts.
  • Person with appropriate electrical training: inspect what is behind the wall panelling above the sub-distribution board.
  • Mark the centres of the ceiling beams.
  • Mark the positions of the ceiling hangers using the drawing.
  • Install the ceiling hangers.
  • Align the door fittings
  • Inspect the outdoor advertising and dismantle it if necessary, except for the small sign. (I found an empty chat for this, is there also a pad?)