G18 Infra
- Cleaning the bathroom and laying down fleece.
- Lay the skirting boards.
- Lay the network cables from the sub-distribution board to the parapet ducts.
- Person with appropriate electrical training: inspect what is behind the wall panelling above the sub-distribution board.
- Mark the centres of the ceiling beams.
- Mark the positions of the ceiling hangers using the drawing.
- Install the ceiling hangers.
- Align the door fittings
- Inspect the outdoor advertising and dismantle it if necessary, except for the small sign. (I found an empty chat for this, is there also a pad?)